AMR goods-to-person retrofit
Harborline Cold Chain (sample business) · Columbus, OH distribution center, leased, 310,000 sq ft
Passport v3 · Last updated Oct 2, 2026
Complete, Confirmed Sep 16
Complete, Completed Sep 24
Complete, 3 providers, Sep 25
In progress, 3 of 3 proposals in
Not started, After you shortlist
Not started, Target Jan 2027
Not started, Target Q1 2027
Next action
Choose a priority and shortlist proposals
Shortlisted providers move to formal underwriting. The earliest proposal expires Oct 24. Owner: Dana Whitfield, CFO · Due Oct 9, 2026
Closing preview
What closing would look like if you selected Provider B. Nothing here is selected, signed, or funded.
Conditions before funding
- Complete
Interim financials through August 2026
Owner: Dana Whitfield, CFO
- Open
Landlord waiver signed
Owner: Priya Nair, Facility Manager
- Open
Authorized signer certificate
Owner: Dana Whitfield, CFO
- Later
Vendor acceptance certificate before final funding
Owner: Jordan Kim, Lakeshore project manager
Vendor funding milestones
| Milestone | Share | Amount | Trigger | Target |
|---|---|---|---|---|
| Order placed | 30% | $444,000 | Signed lease schedule and vendor invoice | Jan 2027 |
| Equipment delivered | 50% | $740,000 | Delivery receipt signed by customer | Mar 2027 |
| System accepted | 20% | $296,000 | Acceptance test passed; certificate signed | Jun 2027 |
Steps to funding
- 1Provider issues final approval and documents
- 2Authorized signer reviews and signs
- 3Provider pays the vendor at each milestone
- 4Customer signs acceptance; payments begin