AMR goods-to-person retrofit
Harborline Cold Chain (sample business) · Columbus, OH distribution center, leased, 310,000 sq ft
Passport v3 · Last updated Oct 2, 2026
Complete, Confirmed Sep 16
Complete, Completed Sep 24
Complete, 3 providers, Sep 25
In progress, 3 of 3 proposals in
Not started, After you shortlist
Not started, Target Jan 2027
Not started, Target Q1 2027
Next action
Choose a priority and shortlist proposals
Shortlisted providers move to formal underwriting. The earliest proposal expires Oct 24. Owner: Dana Whitfield, CFO · Due Oct 9, 2026
Compare proposals
Three synthetic proposals on the same assumptions. Coverage and cash come first, because a lower rate can still leave you paying more of the project yourself.
Scenario
Scenarios change your assumptions only. They never change a provider's terms.
Proposals in ranked order
- Conditional
#1
Provider C
FMV operating lease
Best for: Lowest cash at close
- Financed
- $1.5M · 100%
- Cash at close
- $53,222
- Monthly
- $26,361
- Total to own
- $1,804,147
- Term
- 60 months
- Funding
- ~25 days
Expires Nov 6, 2026
- Conditional
#2
Provider B
Finance lease, $1 buyout
- Financed
- $1.5M · 100%
- Cash at close
- $62,338
- Monthly
- $30,794
- Total to own
- $1,848,406
- Term
- 60 months
- Funding
- ~18 days
Expires Oct 24, 2026
- Indicative
#3
Provider A
Equipment finance agreement
- Financed
- $1.2M · 82%
- Cash at close
- $268,900
- Monthly
- $24,840
- Total to own
- $1,759,325
- Term
- 60 months
- Funding
- ~21 days
Expires Oct 30, 2026
Full comparison
| Item | Provider CBest for lowest cash at close | Provider B | Provider A |
|---|---|---|---|
| Economics | |||
| Amount financed | $1,480,000 | $1,480,000 | $1,213,600 |
| Project coverage | 100% | 100% | 82%Exception: $266,400 of the project is not financed |
| Cash at close | $53,222 | $62,338 | $268,900 |
| Monthly payment | $26,361 | $30,794 | $24,840 |
| Rate, fixed (implicit for leases) | 7.2% | 9.1% | 8.4% |
| Term | 60 months | 60 months | 60 months |
| Fees | $500 | $750 | $2,500 |
| Scheduled payments | $1,581,647 | $1,847,655 | $1,490,425 |
| Required end payment | $0 | $1 | $0 |
| Total financing cost | $102,147 | $368,406 | $279,325 |
| Total outlay to own | $1,804,147Exception: Includes an estimated $222,000 fair-market-value purchase | $1,848,406 | $1,759,325 |
| Present value to own at 8% | $1,466,916 | $1,539,586 | $1,493,990 |
| Security and ownership | |||
| Product | FMV operating lease | Finance lease, $1 buyout | Equipment finance agreement |
| Ownership | Lessor owns; purchase option at term end | Lessor owns until $1 buyout | Customer owns from day one |
| End of term | Return, renew, or buy at fair market value | Title transfers for $1 | Owned outright after final payment |
| Security | Lessor title plus one-payment security deposit | UCC filing on financed equipment only | Equipment lien plus corporate guaranteeException: Guarantee required |
| Prepayment | Early termination per schedule | Early buyout at remaining payments less 3% | 2% penalty in years 1-2 |
| Timing and certainty | |||
| Status | Conditional | Conditional | Indicative |
| Time to terms | 7 business days | 5 business days | 3 business days |
| Funding after selection | About 25 days (provider estimate) | About 18 days (provider estimate) | About 21 days (provider estimate) |
| Proposal expires | Nov 6, 2026 | Oct 24, 2026 | Oct 30, 2026 |
| Conditions |
|
|
|
What each proposal covers
Every cost class in the confirmed quote, and the cash you would still need.
| Cost class | Provider C | Provider B | Provider A |
|---|---|---|---|
| Hard asset$992,000 quoted | Covered$992,000 · 100% | Covered$992,000 · 100% | Covered$992,000 · 100% |
| Technology$118,000 quoted | Covered$118,000 · 100% | Covered$118,000 · 100% | Covered$118,000 · 100% |
| Soft cost$335,000 quoted | Covered$335,000 · 100% | Covered$335,000 · 100% | Partial$103,600 · 31% |
| Service$35,000 quoted | Covered$35,000 · 100% | Covered$35,000 · 100% | Not covered$0 · 0% |
| Cash you still need | $0All quoted costs; residual set on hardware only | $0All quoted costs, within a 35% soft-cost limit | $266,400Soft costs capped at $103,600; prepaid service excluded |
Flexibility after closing
| Right | Provider C | Provider B | Provider A |
|---|---|---|---|
| Prepay or buy out early | PartialEarly termination per schedule | YesRemaining payments less 3% | Partial2% penalty in years 1-2, then free |
| Add equipment on the same terms | YesMaster-lease schedules for added units | YesAdd-on schedule on the same pricing basis for 12 months | NoNew agreement for each addition |
| Move equipment to another site | PartialWith lessor consent | YesWith 30 days' notice | PartialWith lender consent |
| Upgrade or refresh technology | YesUpgrade option at month 36 | NoNot offered | NoNot offered |
| Flexibility points | 6 of 8 | 6 of 8 | 2 of 8 |
How each number is calculated
Project coverage
Amount financed ÷ total installed cost
- Provider C: $1,480,000 ÷ $1,480,000 = 100%
- Provider B: $1,480,000 ÷ $1,480,000 = 100%
- Provider A: $1,213,600 ÷ $1,480,000 = 82%
Cash at close
Costs not financed + fees + advance payments + security deposit. No incentives are confirmed, so none are subtracted.
- Provider C: $0 + $500 + 1 × $26,361 + $26,361 = $53,222
- Provider B: $0 + $750 + 2 × $30,794 + $0 = $62,338
- Provider A: $266,400 + $2,500 + 0 × $24,840 + $0 = $268,900
Total financing cost
Scheduled payments + fees + required end payment − amount financed
- Provider C: $1,581,647 + $500 + $0 − $1,480,000 = $102,147
- Provider B: $1,847,655 + $750 + $1 − $1,480,000 = $368,406
- Provider A: $1,490,425 + $2,500 + $0 − $1,213,600 = $279,325
Total outlay to own
Costs not financed + fees + scheduled payments + the payment needed to own at term end. Advance payments count toward the scheduled payments; the refundable deposit is excluded.
- Provider C: $0 + $500 + $1,581,647 + $222,000 = $1,804,147
- Provider B: $0 + $750 + $1,847,655 + $1 = $1,848,406
- Provider A: $266,400 + $2,500 + $1,490,425 + $0 = $1,759,325
Present value to own
Each dated cash flow discounted monthly at your 8% rate. Taxes and depreciation are excluded; ask a tax advisor.
- Provider C: $1,466,916 at 8%
- Provider B: $1,539,586 at 8%
- Provider A: $1,493,990 at 8%
Same inputs, currency, and date convention for every proposal: monthly payments in arrears, a 60-month term, and amounts in U.S. dollars.
Shortlist and next step
Select up to three proposals above to move them to formal underwriting.
Indicative and conditional terms are not commitments to lend or lease. Final approval, pricing, and documentation remain with each provider.