AMR goods-to-person retrofit

Harborline Cold Chain (sample business) · Columbus, OH distribution center, leased, 310,000 sq ft

See this project as a capital provider

Terms received

Passport v3 · Last updated Oct 2, 2026

  1. Quote review

    Complete, Confirmed Sep 16

  2. Passport

    Complete, Completed Sep 24

  3. Consent and matching

    Complete, 3 providers, Sep 25

  4. Compare terms

    In progress, 3 of 3 proposals in

  5. Underwriting

    Not started, After you shortlist

  6. Closing

    Not started, Target Jan 2027

  7. Funded

    Not started, Target Q1 2027

Next action

Choose a priority and shortlist proposals

Shortlisted providers move to formal underwriting. The earliest proposal expires Oct 24. Owner: Dana Whitfield, CFO · Due Oct 9, 2026

Compare proposals

Project passport

One standardized record of the business, facility, project, and request. Every value shows where it came from, so providers can see what is confirmed and what is not.

Business

90% complete
Legal name
Harborline Cold Chain LLC (sample)Source: Formation documents
Customer confirmed
Entity and state
LLC, Ohio, formed 2009Source: Formation documents
WareFin reviewed
Industry
Refrigerated warehousing, NAICS 493120
WareFin reviewed
Revenue, FY2025
$140,000,000Source: FY2025 statements, p.4
Customer confirmed
EBITDA, FY2025
$15,400,000Source: FY2025 statements, p.4
Customer confirmed
Total debt
$28,600,000 vs $28,642,000Source: Balance sheet vs debt schedule
Conflict
Employees
410 across 2 sites
Customer confirmed

Facility

95% complete
Site
Columbus, OH distribution center
Customer confirmed
Control
Leased through 2031Source: Facility lease, p.1
WareFin reviewed
Size
310,000 sq ft; ambient, chilled, frozen zones
Customer confirmed
Operations
3 shifts, 6 days; peak in Q4
Customer confirmed
Landlord consent
Not provided
Not found
Charger power
Capacity confirmed by integratorSource: Quote v2, p.4
Extracted

Project

100% complete
Scope
14 AMRs, 4 goods-to-person stations, fleet and WES softwareSource: Quote v2, p.3-5
Customer confirmed
Integrator
Lakeshore Automation (sample integrator)
WareFin reviewed
Schedule
Order Jan 2027; install Mar-May; go-live Jun 2027Source: Quote v2, p.9
Extracted
Acceptance test
1,150 order lines per hour for 5 consecutive daysSource: Statement of work, p.6
Customer confirmed
Vendor payment terms
30% at order, 50% at delivery, 20% at acceptanceSource: Quote v2, p.9
Customer confirmed

Costs

100% complete
Total installed cost
$1,480,000Source: Quote v2 reconciliation
Customer confirmed
Hard assets
$992,000 (67%)
WareFin reviewed
Software
$118,000 perpetual license (8%)
Customer confirmed
Soft costs and service
$370,000 (25%)
WareFin reviewed
Sales tax
Equipment exemption claimed; certificate on file
Customer confirmed

Business case

85% complete
Annual labor and overtime benefit
$520,000 at full run rateSource: Vendor ROI model
Extracted
Added operating cost
$90,000 per year
Customer confirmed
Ramp to full benefit
6 months after go-live
Customer confirmed
Benefit basis
Vendor estimate; customer baseline pending
Not found

Financing request

100% complete
Amount requested
$1,480,000
Customer confirmed
Structures considered
Loan, EFA, finance lease, FMV lease
Customer confirmed
Preferred term
48 to 72 months
Customer confirmed
Cash contribution
Up to $150,000
Customer confirmed
Funding needed
Q1 2027
Customer confirmed

What each label means

Customer confirmed
You reviewed and approved the value.
WareFin reviewed
The deal desk checked it against a source document.
Extracted
Read from a document; not yet confirmed by a person.
Provider verified
A provider confirmed it during underwriting.
Not found
No source yet. Providers see that it is missing.
Conflict
Two sources disagree. Providers see both values.

Versions

  1. v3 · Sep 24, 2026

    Deal desk validated; shared with Providers A, B, C

  2. v2 · Sep 20, 2026

    Interim financials and facility lease added

  3. v1 · Sep 16, 2026

    Created from confirmed quote v2

Providers always see the version you approved. A material change creates a new version and asks before sharing it.